Building control measurements

Building site marking (terrain marking)

In building site marking the location of the building is marked at the construction site.

The site  marking can only be ordered once the building permit has been granted. Also check that site marking is a requirement in the permit regulations.

Timing of building site marking

The building site marking (terrain marking) must be ordered before the actual construction work begins.

There is no service in building control measurements between 8.7.2024 – 19.7.2024.

The time of the marking measurement should be chosen so that the construction area has been cleared, the surface soil has been peeled and any gravel mattress has been spread out.

However, do not start earthmoving work at the construction site if the boundaries are unclear. If the boundaries of the construction site are unclear, you can order a boundary marking by email from kiinteistonmuodostus@kuopio.fi.

There are no additional costs for the builder for marking the boundaries for preliminary earthmoving work on the construction site.

Location review

The location review can be ordered when the exterior walls of the building are in place.

In the location review the building’s location and elevation are being checked.

Fees

Fees for building control measurements are being charged in connection with the building permit fee.

Contact information

Real estate formation

PL 1097 70111 Kuopio